XPS beneath a raft foundation: information the designer needs

XPS insulation

At a glance

XPS beneath a raft foundation provides insulation and forms part of the load path from the house into the ground. To specify it, the designer needs ground and groundwater information, the load layout and evidence of XPS behaviour under sustained pressure. Mark slab edges, columns and service penetrations on the foundation plan from the outset. At these locations, a thickness alone does not define the support, the connection to plinth insulation or how to keep the waterproofing continuous.

Yellow XPS boards with smooth faces and square edges

Establish the ground conditions

Start with the site’s geotechnical information. Changing the XPS grade neither removes a weak soil layer nor replaces the specified sub-base.

Where the design uses perimeter insulation for frost protection, show its route at the entrance and terrace. Service trenches may interrupt the strip.

Mark wall and column loads

Distinguish distributed loads, bearing walls and columns on the foundation plan. Dividing total house weight by floor area does not describe the local bearing conditions.

For permanent loads the designer checks creep and permissible movement, among other factors. A short-term compression class cannot answer that question alone.

Continue insulation around the slab edge

Trace the junction from horizontal XPS beneath the raft to the wall insulation on the plinth section. Pay attention to any step beneath the patio doors.

Use the ordered grade’s thickness and conductivity in the thermal assessment. Show local reductions on the drawing rather than assigning one thickness across the raft.

Coordinate waterproofing and pipes

Low XPS water absorption does not seal a drainpipe penetration. Show what the seal connects to and who will inspect it.

Check membrane, adhesive and XPS compatibility for the specified system. If a separating layer is required, allow space for it even between closely spaced services.

Prepare for reinforcement work

Check sub-base level and flatness before the first row. A board bridging a hollow will not gain sound bearing simply because it is loaded later.

Define access routes to protect board corners while reinforcement is carried in. Correct any damage while the insulation joints remain visible, before placing the steel.

Locate sleeves from fixed reference points, not from loose boards. That allows movement during the work to be detected.

State the intended loadbearing use

State that the boards go under a loadbearing raft, together with thickness, edge profile and required design properties. Obtain documentation covering this use.

If the offer says only “floor insulation”, compare its scope with the specification before unloading. A domestic floor and the foundation of the whole house are different load cases.

7 branches. Materials closer to your project.

  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]
Budowlanka.org — map

Free quote

What to include in your enquiry

Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.

More from the building guide