Buying PIR boards: how to spot an incomplete insulation quote
PIR insulation
Ask what will be finished when the crew leaves. A square metre of PIR does not include substrate preparation, fixings or sealed junctions unless the quote says so. Boards that look alike can differ in facing, strength and intended use. Before ordering, obtain the current technical data sheet, declaration of performance and installation instructions for the exact variant. Name it on the order and match it to the pack labels before the delivery is split between rooms. Then compare the cost of two complete installations, not the price of boards delivered to the kerb against a finished job.

Link the documents to the delivered variant
Check thickness, edge profile and board type. Resolve discrepancies before installation. Keep a label photograph and delivery note so the concealed layer can still be identified later.
Compare equivalent scopes
Compare declared resistance at the offered thickness and the facing’s connection to the next layer in separate columns. Equal thickness does not guarantee equal resistance; equal conductivity does not prove adhesive compatibility. Mark supply-only and installed prices.
List preparation, boards, accessories, labour, waste disposal and site protection. Then check whether a lower total represents a saving or a missing service. Both proposals should leave the house with the same specified result.
Board size and access
Check pack dimensions against the narrowest doorway and stair turn. Large sheets cover an open area quickly but corners are vulnerable on a tight staircase. Smaller boards may be easier despite the higher piece count.
Walk the route from lorry to installation point and identify a dry storage area. Easy loading onto the truck does not imply easy handling inside; excessive stock can obstruct the work.
Cutting plan and edge joints
Lay out full boards along the longest straight run before marking recesses, returns and openings. At every cut check whether the tongue, groove, lap or straight edge remaining will mate with the next board.
A rectangular area and a room with alcoves need different allowances. Retain usable offcuts for identified positions, but do not build critical details from assorted scraps merely to reduce waste.
Who supplies tapes, adhesive and fixings?
For each tape, adhesive or fixing, note the surfaces it joins and who selects it. Taping a facing, bonding a substrate and anchoring into structure require different compatibility checks.
If the owner buys boards and the installer buys accessories, agree on the combination before work. Record who supplies each item so an incompatible component is not improvised after the layer is concealed.
Costs and handover
Schedule inspection of substrate, boards and connections before concealment. Price protection, cutting and accessories too. Agree these steps before payment so acceptance covers installation and not just the number of packs.
Use location-labelled photographs rather than unidentifiable close-ups. At handover, ask for a record of the completed build-up. It will be more useful during repairs than a material invoice alone.
Worked example: checking quantities
For 90 m², a 1,200 × 600 mm board covers a nominal 0.72 m², giving a geometric minimum of 125. At 2,400 × 1,200 mm the nominal area is 2.88 m²: just over 31 boards, hence at least 32 whole boards. These figures omit edge profiles, effective coverage, cuts and waste. Order from the layout and list joint foam separately; it is an accessory, not a replacement for boards.
Free quote
What to include in your enquiry
Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.
More from the building guide
Therma TF70 is a PIR board for floor insulation. In a house with a low patio threshold, work down from the finished…
A factory-cut window opening saves site work only if the window size and position are agreed in time. Cutting an opening changes…
Conductivity (lambda), thermal resistance (R) and thermal transmittance (U) answer different questions. The declared conductivity, usually marked λD, describes a particular product.…
Compare PIR and EPS cores using the declared performance of complete roof sandwich panels, not figures for loose insulation boards. U-values, weight,…
An energy-efficient house should allow seals to be repaired, drains to be inspected and installations to be serviced without unnecessarily dismantling large…
Internal insulation can be considered when an older masonry building's facade must remain unchanged. Its suitability depends on the existing construction: thick…
Building quotations become comparable only when they cover the same work, materials and completion requirements. A low total may omit unloading, weather…
Mark the intended insulation position on a section through the roof. Between uneven rafters, the material must fill each bay closely. Above…