Utherm Roof BM on a flat roof: which facing meets the waterproofing?
PIR insulation
Utherm Roof BM has two different surfaces: bituminised glass fleece on one side and mineralised glass fleece on the other. When ordering for a flat roof, request a section identifying both faces and the first waterproofing layer. This lets the roofer check compatibility and plan the installation sequence. For thickness selection, read the corresponding row in the BM sheet because conductivity varies with thickness. A comparison with foil-faced insulation therefore needs both the thermal resistance and the proposed connection to the roof system.

Identifying the two faces of Roof BM
Inspect both facings with the roofer when opening the first pack. Record the Roof BM designation and identify the face intended for the chosen waterproofing on the drawing.
How conductivity changes with thickness
The manufacturer gives λD of 0.027 W/(m·K) below 80 mm, 0.026 from 80 to below 120 mm, and 0.024 from 120 mm. Check the applicable band whenever thickness changes.
The table gives RD of 3.80 m²K/W at 100 mm and 5.00 m²K/W at 120 mm. Weigh that gain against the extra 20 mm needed at waterproofing terminations.
Laying square-edged insulation
Roof BM measures 1200 × 600 mm with four square edges. At a rectangular rooflight, arrange joints in adjacent courses so the pieces beside the kerb are stable and supported.
When cutting around a penetration, mark the top face on every piece. A flipped offcut may fit the outline yet put the opposite facing beneath the membrane.
Waterproofing contact and installation sequence
Use the roofing system documentation to establish how the first waterproofing layer is fixed. Bitumen in a facing does not by itself approve any particular heating technique.
Before starting a section, confirm the surface is clean and dry. Compare the fixing pattern in the field with the requirements at edges and corners.
Interpreting CS150 and fire class F
BM is listed with a compressive stress of at least 150 kPa at 10% deformation and reaction to fire class F. The former is a board compression test result, the latter a product fire classification.
Request evidence for the actual roof assembly at handover. Alongside zones carrying equipment, identify provisions for protecting the waterproofing during maintenance.
Specifying and pricing Roof BM
Specify Roof BM, thickness and waterproofing type in the enquiry. Include parapet and penetration details so accessory quantities reflect the actual junctions.
When comparing BM with foil-faced insulation, include the specified adhesives, fixings and edge work. A facing change can alter roofing cost even at a similar board price.
Checking a proposed substitute
If the delivery differs from the schedule, set that batch aside until both faces have been checked against the design. Keep the label and photographs of both sides of the proposed substitute.
Free quote
What to include in your enquiry
Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.
More from the building guide
Planning PIR insulation should begin by identifying which rooms will belong to the heated part of the house. The roof, a ceiling…
Choose termPIR WS together with the waterproofing and fixing method for the flat roof. The rigid PIR core is faced on both…
White 100 mm PIR wall panels can suit many projects, but an outlet batch must be assessed individually. Documentation, joint and facing…
A single window reveals much about how IDELCO α-therm WALL fits into a cavity wall. A section below the sill shows where…
Therma TF70 is a PIR board for floor insulation. In a house with a low patio threshold, work down from the finished…
Mark the intended insulation position on a section through the roof. Between uneven rafters, the material must fill each bay closely. Above…
Three layers meet a rooflight kerb. EFYOS BLUE A insulation must reach it as shown on the thermal detail. The vapour control…
Before installing swissporPIR Alu on a flat roof, establish the deck, falls and fixing method. The manufacturer requires mechanical fixings even where…