A SOPREMA PIR roof at a rooflight: who completes each layer?

PIR insulation

At a glance

Three layers meet a rooflight kerb. EFYOS BLUE A insulation must reach it as shown on the thermal detail. The vapour control layer needs a connection on the side specified by the designer, while the waterproofing must return rainwater to the roof surface. If different trades install the layers, mark the trade and inspection point for each connection on a single section. Inspect during installation. Once the final membrane is in place, two of the three connections are generally concealed.

SOPREMA EFYOS BLUE A insulation beneath the roof waterproofing

What to settle before delivery

Before delivery agree who prepares the vertical face and what each layer connects to. Otherwise two trades may end their work at different points.

Identifying the board and its declared properties

EFYOS BLUE A has a PIR core, two aluminium facings, λD 0.022 W/(m·K), CS(10/Y)120 and reaction-to-fire class E. Specify the membrane, vapour control layer and attachment method from the roof system documents.

Using a worked example

First inspect where the vapour control layer meets the kerb and how the corner is sealed. Then check the fitted boards and cut edges. Finally inspect the waterproofing upstand, its upper termination and the drainage route around the kerb.

Label photos on a sketch of the four kerb faces. This identifies each inspected side even when work takes place on different days.

Comparing the available options

If a missing connection below the board becomes apparent at insulation stage, agree how to expose it with the responsible installer. Taping the surface does not give access to the substrate intended for the original seal.

Inspection before covering

Walk every side with the drawing before the roof is closed. Pay particular attention to corners and the upslope face where rainwater must pass around the obstruction.

What the quote should cover

Specify vapour seals, PIR cut pieces and membrane flashings at each rooflight. Name the trade protecting unfinished connections between site visits.

Records to keep after completion

At handover keep the material schedule with the photos for each layer. If damp appears years later the record shows both the drainage path and concealed internal connections.

7 branches. Materials closer to your project.

  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]
Budowlanka.org — map

Free quote

What to include in your enquiry

Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.

More from the building guide