A SOPREMA PIR roof at a rooflight: who completes each layer?
PIR insulation
Three layers meet a rooflight kerb. EFYOS BLUE A insulation must reach it as shown on the thermal detail. The vapour control layer needs a connection on the side specified by the designer, while the waterproofing must return rainwater to the roof surface. If different trades install the layers, mark the trade and inspection point for each connection on a single section. Inspect during installation. Once the final membrane is in place, two of the three connections are generally concealed.

What to settle before delivery
Before delivery agree who prepares the vertical face and what each layer connects to. Otherwise two trades may end their work at different points.
Identifying the board and its declared properties
EFYOS BLUE A has a PIR core, two aluminium facings, λD 0.022 W/(m·K), CS(10/Y)120 and reaction-to-fire class E. Specify the membrane, vapour control layer and attachment method from the roof system documents.
Using a worked example
First inspect where the vapour control layer meets the kerb and how the corner is sealed. Then check the fitted boards and cut edges. Finally inspect the waterproofing upstand, its upper termination and the drainage route around the kerb.
Label photos on a sketch of the four kerb faces. This identifies each inspected side even when work takes place on different days.
Comparing the available options
If a missing connection below the board becomes apparent at insulation stage, agree how to expose it with the responsible installer. Taping the surface does not give access to the substrate intended for the original seal.
Inspection before covering
Walk every side with the drawing before the roof is closed. Pay particular attention to corners and the upslope face where rainwater must pass around the obstruction.
What the quote should cover
Specify vapour seals, PIR cut pieces and membrane flashings at each rooflight. Name the trade protecting unfinished connections between site visits.
Records to keep after completion
At handover keep the material schedule with the photos for each layer. If damp appears years later the record shows both the drainage path and concealed internal connections.
Free quote
What to include in your enquiry
Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.
More from the building guide
When choosing swissporPIR Alu, look at a section through two joined boards. FIT/GK has square edges, LAP/SF forms a rebated joint, and…
On a flat roof using SOPREMA EFYOS BLUE A, start at the tightest detail: what height remains at the parapet once insulation…
When the exterior cannot change, termPIR AL GK combines rigid PIR insulation with a 12.5 mm plasterboard lining on the room side.…
PIR boards above the rafters insulate a pitched roof without using up more loft space. Before work begins, agree on the finished…
Start a farm insulation survey by marking the spaces that need different conditions on a floor plan. In a vegetable store, air…
Replacing the covering on a house with a finished loft gives access to the rafters from outside. An over-rafter layer of swissporPIR…
An energy-efficient house should allow seals to be repaired, drains to be inspected and installations to be serviced without unnecessarily dismantling large…
A passive house reduces energy demand through coordinated insulation, airtightness, windows, thermal-bridge detailing and controlled ventilation. Thick roof insulation or a large…